This trailer came to us with a failing floor and a tired interior. The slider below shows the main room from the same spot: stripped to the studs with the subfloor going down, then three weeks later with the walls closed in and new plank flooring down. Paint and crown molding are still to come.
Main room


Kitchen end and side doorway


The same end of the home, with the side doorway on the right as the landmark. Before: floor framing open to the ground and walls down to the studs. After: solid floor, walls closed in and ready for paint, and the kitchen opened to the living area.
Latest photos
The kitchen cabinets are going in, the back room has its new floor, door and closet, and the new beam is in place. Paint and crown molding are still to come.




Stage one: gut and subfloor
The crew stripped the rooms back to the studs and joists, cut out the damaged subfloor, repaired the floor framing, and laid new plywood while the plumbing and electrical runs were open and easy to reach.





Stage two: insulation, drywall, doors and trim
With the floor solid, the exterior walls were insulated and drywalled, new prehung interior doors were hung and squared with a laser level, and the trim was cut and fitted on site.






Stage three: flooring down, paint and crown molding next
Wood-look plank flooring is down through the main living areas and the windows and sliding door are in. A new beam has been installed and boxed in across the ceiling, and the kitchen cabinets are going in. Still to do: painting the walls and ceilings and adding crown molding. This page will be updated when the job wraps.